Court of Appeal held that where no payment schedule was agreed for post-practical-completion period, contractor had no right to interim payment notices under the Housing Grants Act 1996 payment regime.
construction
Court of Appeal affirmed the validity of a statutory levy imposed by the Construction Industry Council for lift and escalator maintenance works.
Judicial determination required to assess the extent to which retention monies may be withheld under construction contracts.
Court interpreted Part 5 of the Construction Industry Council Ordinance in a construction industry regulatory dispute.
Get a detailed analysis of Balfour Beatty Regional Construction Ltd v Grove Developments Ltd and how it applies to your situation.
Explain Balfour Beatty Regional Constr...