ISG Construction Ltd v Seevic College

[2014] EWHC 4007 (TCC)
JurisdictionUnited Kingdom
CourtHigh Court (Technology and Construction Court)
Year2014
StatusBinding authority

Summary

Under a JCT Design and Build contract, practical completion is achieved notwithstanding latent defects, limiting the employer's right to withhold payment.

Key Principle

JCT Design and Build; practical completion; latent defects; employer's right to withhold

Area of Law

construction

Related Cases

KONE Elevator (HK) Ltd v Construction Industry Council [2026] HKCA 115

Court of Appeal affirmed the validity of a statutory levy imposed by the Construction Industry Council for lift and escalator maintenance works.

Hip Hing Construction Company Limited v Hong Kong Airlines Ltd [2024] HKCFI 370

Judicial determination required to assess the extent to which retention monies may be withheld under construction contracts.

Kone Elevator (HK) Ltd v Construction Industry Council [2023] HKDC 1216

Court interpreted Part 5 of the Construction Industry Council Ordinance in a construction industry regulatory dispute.

Ask CommonBench about this case

Get a detailed analysis of ISG Construction Ltd v Seevic College and how it applies to your situation.

Explain ISG Construction Ltd v Seevic ...