Summary

Under HGCRA 1996 s 111, a payee's insolvency before the final date for payment extinguishes the payer's obligation to pay the notified sum, overriding the right to suspend for non-payment.

Key Principle

HGCRA 1996 s 111; right to suspend for non-payment; insolvency interaction with adjudication

Area of Law

construction

Related Cases

KONE Elevator (HK) Ltd v Construction Industry Council [2026] HKCA 115

Court of Appeal affirmed the validity of a statutory levy imposed by the Construction Industry Council for lift and escalator maintenance works.

Hip Hing Construction Company Limited v Hong Kong Airlines Ltd [2024] HKCFI 370

Judicial determination required to assess the extent to which retention monies may be withheld under construction contracts.

Kone Elevator (HK) Ltd v Construction Industry Council [2023] HKDC 1216

Court interpreted Part 5 of the Construction Industry Council Ordinance in a construction industry regulatory dispute.