Triple Point Technology Inc v PTT Public Co Ltd

[2021] UKSC 29
JurisdictionUnited Kingdom
Year2021
Statusunclear

Key Principle

Liquidated damages clause accrues up to date of termination for delay. After termination, employer can claim general damages for delay and defective work.

Area of Law

contract

Related Cases

Mann v Paterson Constructions Pty Ltd (2019) 267 CLR 560
Paciocco v Australia and New Zealand Banking Group Ltd (2016) 258 CLR 525
Simic v New South Wales Land and Housing Corporation (2016) 260 CLR 85