United Kingdom liquidated damagesdelay damageslimitation of liability

Triple Point Technology Inc v PTT Public Co Ltd

[2021] UKSC 29
JurisdictionUnited Kingdom
CourtUnited Kingdom Supreme Court
Year2021
StatusBinding authority

Key Principle

Liquidated damages clause accrues up to date of termination for delay. After termination, employer can claim general damages for delay and defective work.

Area of Law

contract