United Kingdom Leading Case penalty clauses and liquidated damagesbreachexpectation damages

Triple Point Technology Inc v PTT Public Co Ltd

[2021] UKSC 29
JurisdictionUnited Kingdom
CourtUK Supreme Court
Year2021
StatusBinding authority

Summary

Liquidated damages for delay accrue only up to termination; thereafter the employer may claim general damages for delay and defective work.

Key Principle

Liquidated damages clause accrues up to date of termination for delay. After termination, employer can claim general damages for delay and defective work.

Area of Law

contract

Related Cases

Mann v Paterson Constructions Pty Ltd (2019) 267 CLR 560

On termination of a building contract, a builder may recover reasonable value of work done in restitution, subject to the contract price as a ceiling where work was performed under a valid contract.

Paciocco v Australia and New Zealand Banking Group Ltd (2016) 258 CLR 525

Bank late payment fees are not penalties where they represent a genuine pre-estimate of loss or protect a legitimate interest of the stipulating party.

Simic v New South Wales Land and Housing Corporation (2016) 260 CLR 85

High Court of Australia examined the principles governing rectification of written contracts for common intention and unilateral mistake in equity.

Ask CommonBench about this case

Get a detailed analysis of Triple Point Technology Inc v PTT Public Co Ltd and how it applies to your situation.

Explain Triple Point Technology Inc v ...