Henia Investments Inc v Beck Interiors Ltd

[2015] EWHC 2433 (TCC); [2015] BLR 704
JurisdictionUnited Kingdom
CourtEngland and Wales High Court (Technology and Construction Court)
Year2015
StatusPersuasive authority

Key Principle

To operate as an Interim Payment Notice under the Housing Grants, Construction and Regeneration Act 1996 regime a contractor's interim application must, in substance, form and intent, be free from ambiguity as to the due date and sum claimed; and a Pay Less Notice is not confined to cross-claims and deductions but may deploy the employer's own valuation of the works.

Area of Law

General

Related Cases

TNLC & Anor v Gambling Commission & Ors [2026] EWHC 891 (TCC)
Aabar Holdings S.A.R.L. and others v Glencore Plc and others [2026] EWHC 877 (Comm)
Waterside Class Limited v Mowi ASA & Ors [2026] CAT 32

Ask CommonBench about this case

Get a detailed analysis of Henia Investments Inc v Beck Interiors Ltd and how it applies to your situation.

Explain Henia Investments Inc v Beck I...