Hochster v De La Tour

(1853) 2 E&B 678
JurisdictionUnited Kingdom
CourtCourt of Queen's Bench
Year1853
StatusBinding authority

Summary

An innocent party may commence an action for breach immediately upon anticipatory repudiation, without waiting for the date fixed for performance.

Key Principle

anticipatory repudiatory breach; the innocent party may sue immediately without waiting for the date of performance

Area of Law

Contract — Breach and Remedies

Related Cases

Cavendish Square Holding BV v Talal El Makdessi [2015] UKSC 67

The UKSC reformulated the penalty clause rule, replacing the Dunlop test with a legitimate interest test asking whether the clause is extravagant or unconscionable relative to that interest.

Transfield Shipping Inc v Mercator Shipping Inc (The Achilleas) [2008] UKHL 48

Remoteness of damage in contract may depend on whether the defendant assumed responsibility for the type of loss, not merely reasonable contemplation.

Golden Strait Corporation v Nippon Yusen Kubishika Kaisha (The Golden Victory) [2007] UKHL 12

Where a charterparty was repudiated, damages are assessed by reference to subsequent events that would have terminated the contract early, reducing the award accordingly.