An innocent party may commence an action for breach immediately upon anticipatory repudiation, without waiting for the date fixed for performance.
Contract — Breach and Remedies
The UKSC reformulated the penalty clause rule, replacing the Dunlop test with a legitimate interest test asking whether the clause is extravagant or unconscionable relative to that interest.
Remoteness of damage in contract may depend on whether the defendant assumed responsibility for the type of loss, not merely reasonable contemplation.
Where a charterparty was repudiated, damages are assessed by reference to subsequent events that would have terminated the contract early, reducing the award accordingly.