UES Holdings Pte Ltd v KH Foges Pte Ltd

[2018] SGCA 39
JurisdictionSingapore
CourtSingapore Court of Appeal
Year2018
StatusBinding authority

Summary

Under Singapore's SOP Act, an adjudication determination on an earlier payment claim does not create issue estoppel barring a subsequent claim for the same work.

Key Principle

SOP Act; repeat payment claims; whether adjudication determination on earlier claim creates issue estoppel for subsequent claim

Area of Law

construction

Related Cases

KONE Elevator (HK) Ltd v Construction Industry Council [2026] HKCA 115

Court of Appeal affirmed the validity of a statutory levy imposed by the Construction Industry Council for lift and escalator maintenance works.

Hip Hing Construction Company Limited v Hong Kong Airlines Ltd [2024] HKCFI 370

Judicial determination required to assess the extent to which retention monies may be withheld under construction contracts.

Kone Elevator (HK) Ltd v Construction Industry Council [2023] HKDC 1216

Court interpreted Part 5 of the Construction Industry Council Ordinance in a construction industry regulatory dispute.

Ask CommonBench about this case

Get a detailed analysis of UES Holdings Pte Ltd v KH Foges Pte Ltd and how it applies to your situation.

Explain UES Holdings Pte Ltd v KH Foge...